Crane Gantry Construction and Hard Standings at Peterlee

AM&G Construction was engaged by the Client to construct approximately 1300 m2 of new reinforced concrete hard standings as well as the foundations for a new overhead crane gantry for their steel fabrication facility.

The crane gantry construction was undertaken in 2009

Principal activities included:-

  • Excavation and disposal of soils. Setting out and survey control
  • Construction of new pad foundations and HD bolts for new crane gantry.
  • Construction of reinforced concrete bays for new hard standings and lay down areas.
  • Installation of new pits to existing factory for shot blasting equipment.